Skip to content
KWBG Radio | Boone, Iowa

KWBG Radio | Boone, Iowa

Boone's Local News Radio

Primary Menu
  • News
    • Local News
    • Funeral Announcements
    • Reports
      • Boone County Sheriff’s Office
      • Boone PD Reports
      • Ogden PD Reports
      • Madrid PD Reports
      • County Attorney’s Reports
      • Fuel Reports
  • Sports
    • Local
    • State
    • Broadcast Schedule
    • Listen Live to Local Sports
  • Weather
    • Forecast
    • Closings and Postponements
    • Weather Archives
    • Road Conditions
  • Calendar
  • Audio
    • Listen Live
    • Tuned In
    • Coaches Corner
    • Special Podcasts
  • About
    • Contest Rules
    • Job Openings
    • Legal/EEO
    • FCC Applications
    • Contact Us
    • Bill Pay
  • Job Search
  • Puzzles
Live
  • Local News

DMACC Boone Campus Student Activity Center Progressing

KWBG 05/21/20

BOONE, Iowa—The current coronavirus pandemic has not held up construction on the DMACC Boone Campus Student Activity Center.  In fact, mild weather conditions this spring has allowed construction to move ahead quickly.

Here’s a drone shot of the Boone Campus Student Activity Center project before the structural steel and precast wall panel erection has begun.

 

 

 

 

 

 

 

 

The $6.5 million project includes two college-size basketball / volleyball courts. These courts also contain 3 40’ X 70’ baseball / softball batting cages that drop down from the fieldhouse ceiling.  The new student activity center also contains a state-of-the-art weight room designed by Powerlift, a contemporary sports medicine lab, an indoor golf performance center, storage space, office settings, and a family room.

A large crane is used to place the precast wall panels into place.

 

 

 

 

 

 

 

 

 

Precast wall panels are being attached to the existing facility, which adds an additional 28,500 square feet to the existing gym.

 

 

 

 

 

 

 

 

The structural steel and precast panel erection continues on the Boone Campus Athletic building.

 

 

 

 

 

 

 

 

The structural steel and precast panel erection continues on the Boone Campus Athletic building.

 

 

 

 

 

 

 

 

DLR Architects and Baxter Construction said they are on schedule to complete this project by this coming September.  The gym and weight room flooring have already been ordered for the facility.

 

(contributed article and photos, DMACC)

 

 

 

 

 

 

 

 

 

 

About the Author

Avatar photo

KWBG

Administrator

View All Posts

Post navigation

Previous: KWBG Classic Sports for May 23rd and 24th
Next: Jim Uthe, Democratic Candidate for Boone County Supervisor in the June 2nd Primary Election

Related Stories

KWBG Local News
  • Local News

Boone Fire Department Part of Mutual Aid Call for Story City Fire Department, Follows Up with Structure Fire on Tuesday

KWBG 04/02/26
KWBG Local News
  • Local News

Weather Service Updates Information for Possible Hazardous Weather

KWBG 04/01/26
KWBG Local News
  • Local News

Boone Water Works Releases Consumer Confidence Water Quality Report

KWBG 03/31/26
Copyright © 2025 KWBG - All rights reserved.